What comes before construction on a mall store?
Three sets of approval. The retailer issues its brand drawings, the landlord reviews them against its tenant criteria, and the municipality reviews them for a building permit: Hamilton's route starts with its small-business building permit guidance. Electrical work also needs a notification to the Electrical Safety Authority, filed by an electrical contractor holding an ESA licence.
What does a finished mall unit look like?
OAKBERRY Açaí, Lime Ridge Mall, Hamilton



Why do mall fit-outs often run at night?
Because the centre stays open. Most landlords limit noisy work, deliveries and debris removal to hours when the mall is closed, and route materials through the service corridor. That changes crew hours, delivery booking and dust control, so the landlord's rules belong in the price from the start. Working around an open business covers the detail.
What do the retailer's brand drawings decide?
The look and the fixture plan: storefront, flooring, ceiling, lighting, fitting rooms, cash wrap and stock room. A chain usually supplies some items itself, such as fixtures and signage. The bid has to show which items the retailer supplies and which the contractor buys and installs, or two prices cannot be compared.
Who on the site needs WSIB clearance?
Every contractor. The WSIB says a clearance must be in place before any construction work begins and for the duration of the work, and a contractor who hires a subcontractor must get the sub's clearance first. Landlords usually ask for these with the contractor documents. See WSIB clearance certificates.
What does Cruzz need to price a store?
The brand drawing set, the landlord's tenant criteria, the list of retailer-supplied items and the possession and turnover dates. Send them; each trade is priced from the drawings and the price comes back in one package. Spas and golf studios in a plaza follow the same landlord route. A chain opening several stores should read retail rollouts, and the inspections before opening set the last weeks of the schedule.
| Approval | Who gives it | What it covers |
|---|---|---|
| Brand drawings | The retailer | The look, the fixture plan and the items the chain supplies. |
| Tenant criteria review | The landlord | Storefront, materials, services and the rules for building in the centre. |
| Building permit | The municipality | The construction itself, under the Building Code. |
| Electrical notification | The Electrical Safety Authority | The electrical work, filed by the electrical contractor. |